Integra Resources Cuts 2026 Gold Output Guidance After Recovery Slips
As seen on the 24/7 Wall St. homepage on November 11, 2026.
Integra cut full-year gold production guidance to 59,000-62,000 ounces from 70,000-75,000 after leach recovery at Florida Canyon slipped to 52.5% from 60.7%, even as mining hit record rates. Both EPS and revenue came in below expectations, and mining rates are being throttled for the rest of the year to protect the heap leach pads.
Continue ReadingShow less
Integra Resources reported adjusted earnings per share of $0.06 for Q3 2026, missing expectations. Revenue came in at $72.4 million, also missing expectations, though it did edge higher compared with the same quarter a year ago.
The core problem at the Florida Canyon Mine in Nevada was a disconnect between how fast ore was being mined and how effectively it was being processed. Mining rates hit a record average of 97,428 tonnes per day, up from 64,488 tonnes per day in Q3 2025, but leach recovery slipped to 52.5% from 60.7% as a larger share of run-of-mine ore was placed on the heap leach pads. That gap held quarterly gold production to 17,652 ounces and gold ounces sold to 16,760, down from 20,265 in the prior-year period.
The recovery shortfall triggered a significant revision to Integra's full-year production outlook. The company cut its 2026 Florida Canyon gold production guidance to 59,000 to 62,000 ounces from an earlier target of 70,000 to 75,000 ounces. CEO George Salamis said mining rates will be reduced for the remainder of the year to protect long-term heap leach pad performance and maintain effective blending.
Sponsored
On the financial side, net income was $12.9 million, up sharply year over year, though the prior-year comparison was depressed by a $17.7 million non-cash unrealized derivative loss on the convertible debt conversion feature. Operating cash flow fell to $21.8 million, weighed down in part by a $15.3 million increase in working capital from an inventory build-up. The company ended the quarter with $119.5 million in cash and equivalents.
Looking ahead, Integra is positioning the Central Pit as the key catalyst for improvement. Mining is expected to advance into higher-grade ore there in 2027, which management says should stabilize leach rates and support production recovery. The DeLamar project is moving through environmental review under a FAST-41 permitting schedule, with an Environmental Impact Statement and Record of Decision anticipated in the second half of 2027, and GenCap has been engaged to evaluate financing alternatives ahead of a construction decision.