Hut 8 Jumps 9%, MARA Rallies 8% Despite Analyst Cuts; Riot Platforms Rises 2% Despite Downgrade
This post may contain links from our sponsors and affiliates, and Flywheel Publishing may receive compensation for actions taken through them.
Three crypto miners racing to become AI data center providers are rallying even as analysts turn more cautious on the group. Hut 8 (NASDAQ:HUT) stock is trading at $61.78 in afternoon trading, up 9%. That bounce comes after a steep slide, and Hut 8 stock is down 27% over the past month.
MARA Holdings (NASDAQ:MARA | MARA Price Prediction) stock is at $7.93, up 8%. Riot Platforms (NASDAQ:RIOT) stock is at $18.49, up 2%, a smaller gain that falls behind both peers after a sharp recent run. All three drew price target cuts or a downgrade. The moves came in the latest round of analyst notes, and the market is looking past near-term mining weakness toward contracted AI data center backlog.
Analyst Caution Runs Into a Bitcoin and AI Funding Rebound
Analysts downgraded Riot over its substantial reliance on Anthropic as a data center tenant and cut their price targets on Hut 8 and MARA, citing more hurdles for AI data center growth. Needham trimmed its MARA estimates after the company’s Q3 2026 mining miss, reported November 9, but held its rating based on the outlook for high-performance computing (HPC) leasing. Hut 8 had already missed on the top line, with its Q3 revenue of $71.07 million, reported November 4, falling short of the $76.95 million consensus.
Bitcoin (CRYPTO:BTC) is at $74,555, up 1% over the past 24 hours. Tech stocks are also rallying. The move comes after CoreWeave (NASDAQ:CRWV) reported a beat-and-raise quarter on November 10, relieving fears about how AI data center buildouts get funded as the industry shifts toward contract-backed financing and customer prepayments. Funding clarity matters for Hut 8, MARA and Riot as they steer their power and sites toward AI computing. Chicago Fed President Austan Goolsbee called the latest inflation report “borderline disturbing” while the Federal Reserve weighs more rate hikes, which makes the miners’ advance all the more notable.
How MARA and Riot Stack Up Against Hut 8
MARA’s gain is nearly matching Hut 8’s despite Q3 revenue of $164.23 million that missed the $176.13 million consensus. The company’s $1.28 in earnings per share (EPS) topped estimates only because of an $885.30 million unrealized mark-to-market gain on its Bitcoin holdings. Without that gain, the quarter reflected weaker mining economics, as a 37% decline in the average price of Bitcoin mined cut $94.80 million from revenue. After quarter-end, MARA’s board authorized a $500 million share repurchase program.
Riot’s downgrade centers on tenant concentration, and the stock is lagging both Hut 8 and MARA. On August 10, Riot announced a 20-year lease with a leading frontier AI lab that’s expected to generate $9.1 billion in initial contract revenue. Together with a chipmaker tenant at the Rockdale campus, those leases represent $9.8 billion of long-term contracted revenue from just two customers.
Three Different Paths From Mining to AI Data Centers
Hut 8 runs a power-first model, securing power and sites before signing long-term, triple-net, take-or-pay leases with AI tenants at campuses such as River Bend and Beacon Point. Funding for those projects is planned at the project level, a structure designed to limit dilution and parent-company debt for Hut 8 shareholders.
MARA is taking a broader path. It is acquiring the Long Ridge natural gas plant, developing a large Texas site in Matagorda County and selling sovereign private cloud services in Europe through its Exaion subsidiary. Bitcoin mining remains MARA’s operating foundation, keeping its sites productive while those higher-value uses develop.
Riot leans on vertical integration through its ESS Metron and E4A Solutions units, which manufacture power distribution equipment and provide electrical engineering services, and that in-house capability supports Riot’s own data center buildouts and gives the company an engineering business selling into the wider data center market.
Hut 8’s Rebound Rests on Delivering Its AI Campuses
The next test for Hut 8 is whether River Bend’s first data hall arrives in Q2 2027, followed by Beacon Point Phase 1 in Q3 2027. Bulls can point to Hut 8’s expected $26.6 billion in AI data center contract value and its expanded $1 billion buyback authorization. The bears counter that Bitcoin-driven earnings swings, multi-year construction risk and tenant concentration, the same issue behind Riot’s downgrade, could weigh on all three names.
MARA has its own milestones, including closing Long Ridge by year-end and signing two data center leases that management cautions could slip into 2027. Some investors may want to keep their share exposure smaller until the analyst debate over AI data center challenges settles.